First line checks

First line checks

1. Does the client have Power on site?
2. Does the POE unit have Power?
3. Are both network Cables Plugged into the POE?
4. If the service is down:  Remove the Outside Antenna Cable(Connected to the OUT Port) for 30 seconds of the POE and reset it firmly into its seat
(Black Cable, also known as the Connect port. This action resets the Outside Antenna Radio)
5. Is the Antenna Cable connected to the OUT Port of the POE and seated firmly in? (also known as the connect port)
6. Is the Network Cable from the POE on the IN Port is connected onto the WAN port and seated firmly in?
(also known as the ON port)
7. Are both network cable securing connected to the router and POE?
8. Have you rebooted the POE?
9. Have you rebooted the Cisco Router?


    • Related Articles

    • Enlight Sienna / DIN-R PLC Meter

      Attached is the Enlight Sienna training manual and also the short codes.
    • Sensus Prepaid Reference Guide V3A

      To turn on the CIU for the first time remove the paper battery strip located at the back of the CIU in the battery compartment. Pairing the CIU to the Meter On the CIU press #92#. The CIU requests a PIN code. Enter 6171 (default - unless you changed ...
    • Inhemeter Spilt

      Operation manual
    • What to do if meter rejects token

      This SOP applies to all meters PROCEDURE: 1. Meter number: Ask the customer to confirm that the meter number on the token and the meter number on the meter is the same. If the meter number is not shown, the customer can enter the relevant short code ...